Sourcengine has published its Q1 lead time report.
Volatile memory is at 11-17 weeks and going up and NV memory is at 13-19 weeks and is mostly going up or, if not, is stable.
Storage is at 10-15 weeks and mostly going up.
Discretes are at 20-47 weeks and stable
Standard logic and linear are at 7-20 weeks and mostly stable
Advanced analogue is at 23-41 weeks and mostly stable
Embedded processors are 15-48 weeks and mostly stable
Programmable logic is at 20-25 weeks and stable
Here is the full report